In which project life cycle phase should the regulatory impact assessment process begin? Discovery/concept preparation Initiation Planning Execution Closing

In which project life cycle phase should the regulatory impact assessment process begin? Discovery/concept preparation Initiation Planning Execution Closing
In which project life cycle phase should the regulatory impact
assessment process begin?
Discovery/concept preparation
Initiation
Planning
Execution
Closing

Solution
4.2(311 votes)

Answer

Initiation Explanation The regulatory impact assessment process should begin during the Initiation phase, as this is when project objectives are defined and potential regulations that may affect the project are identified.

Explanation

The regulatory impact assessment process should begin during the Initiation phase, as this is when project objectives are defined and potential regulations that may affect the project are identified.