05.10. If an unexpected UST is encountered during construction, what should occur first? A. Call the Illinois State Police. D B. Work shall stop in this area in accordance with 107.19. C. The environmental firm shall contact the DESU. D. The Contractor shall remove the tank so that construction schedules are not affected.

05.10. If an unexpected UST is encountered during construction, what should occur first? A. Call the Illinois State Police. D B. Work shall stop in this area in accordance with 107.19. C. The environmental firm shall contact the DESU. D. The Contractor shall remove the tank so that construction schedules are not affected.
05.10. If an unexpected UST is encountered during construction, what
should occur first?
A. Call the Illinois State Police.
D B. Work shall stop in this area in accordance with 107.19.
C. The environmental firm shall contact the DESU.
D. The Contractor shall remove the tank so that construction schedules
are not affected.

Solution
4.6(136 votes)

Answer

B. Work shall stop in this area in accordance with 107.19. Explanation When an unexpected Underground Storage Tank (UST) is encountered during construction, the first step should be to stop work in that area to ensure safety and compliance with regulations. This allows for proper assessment and handling of the situation.

Explanation

When an unexpected Underground Storage Tank (UST) is encountered during construction, the first step should be to stop work in that area to ensure safety and compliance with regulations. This allows for proper assessment and handling of the situation.