QuestionAugust 25, 2025

True or False Question True or false: Send and receive tasks to forward work are not necessary, since the sending and receiving is indicated by the sequence flow. True False

True or False Question True or false: Send and receive tasks to forward work are not necessary, since the sending and receiving is indicated by the sequence flow. True False
True or False Question
True or false: Send and receive tasks to forward work are not necessary, since the sending and receiving is indicated by the sequence flow.
True
False

Solution
4.1(195 votes)

Answer

False Explanation 1. Understand the role of send and receive tasks Send and receive tasks are used to explicitly define the action of sending or receiving information or work in a process. They provide clarity and specificity beyond what sequence flows can indicate. 2. Evaluate the necessity of send and receive tasks While sequence flows show the direction of process execution, they do not specify the nature of the interaction between tasks. Send and receive tasks are necessary for detailing these interactions clearly.

Explanation

1. Understand the role of send and receive tasks<br /> Send and receive tasks are used to explicitly define the action of sending or receiving information or work in a process. They provide clarity and specificity beyond what sequence flows can indicate.<br />2. Evaluate the necessity of send and receive tasks<br /> While sequence flows show the direction of process execution, they do not specify the nature of the interaction between tasks. Send and receive tasks are necessary for detailing these interactions clearly.