QuestionJune 2, 2025

There is usually no __ or duration associated with a milestone. Select one: a. cost b. resource c. dependency d. verb

There is usually no __ or duration associated with a milestone. Select one: a. cost b. resource c. dependency d. verb
There is usually no __ or duration associated with a milestone.
Select one:
a. cost
b. resource
c. dependency
d. verb

Solution
4.2(259 votes)

Answer

a. cost Explanation Milestones in project management are significant points that mark the completion of a phase or task. They typically do not have associated costs, resources, or dependencies, but they can be described with verbs. Therefore, "cost" is the most fitting answer.

Explanation

Milestones in project management are significant points that mark the completion of a phase or task. They typically do not have associated costs, resources, or dependencies, but they can be described with verbs. Therefore, "cost" is the most fitting answer.