All projects in a portfolio are required to start at the same time and finish together. False True

All projects in a portfolio are required to start at the same time and finish together. False True
All projects in a portfolio are required to start at the same time and finish together.
False
True

Solution
4.7(316 votes)

Answer

False Explanation 1. Evaluate the statement Projects in a portfolio can have different durations and dependencies, so they do not necessarily need to start or finish at the same time.

Explanation

1. Evaluate the statement<br /> Projects in a portfolio can have different durations and dependencies, so they do not necessarily need to start or finish at the same time.