Which of the following is NOT one of the recommended guidelines for developing useful work package estimates? Estimates should include a normal level of contingency. Estimates should be based on normal conditions. Use several people to estimate the same work. Estimates should be made by those responsible for the work. Estimates should be independent of other projects.

Which of the following is NOT one of the recommended guidelines for developing useful work package estimates? Estimates should include a normal level of contingency. Estimates should be based on normal conditions. Use several people to estimate the same work. Estimates should be made by those responsible for the work. Estimates should be independent of other projects.
Which of the following is NOT one of the recommended guidelines for developing useful
work package estimates?
Estimates should include a normal level of contingency.
Estimates should be based on normal conditions.
Use several people to estimate the same work.
Estimates should be made by those responsible for the work.
Estimates should be independent of other projects.

Solution
4.5(330 votes)

Answer

Estimates should be independent of other projects. Explanation 1. Identify the guideline not typically recommended Analyze each option to determine which one is not a standard guideline for developing work package estimates. - "Estimates should include a normal level of contingency" is generally recommended to account for uncertainties. - "Estimates should be based on normal conditions" ensures realistic and achievable estimates. - "Use several people to estimate the same work" helps in getting diverse perspectives and more accurate estimates. - "Estimates should be made by those responsible for the work" ensures accountability and accuracy. - "Estimates should be independent of other projects" is not typically emphasized, as dependencies might exist between projects.

Explanation

1. Identify the guideline not typically recommended<br /> Analyze each option to determine which one is not a standard guideline for developing work package estimates.<br /><br />- "Estimates should include a normal level of contingency" is generally recommended to account for uncertainties.<br />- "Estimates should be based on normal conditions" ensures realistic and achievable estimates.<br />- "Use several people to estimate the same work" helps in getting diverse perspectives and more accurate estimates.<br />- "Estimates should be made by those responsible for the work" ensures accountability and accuracy.<br />- "Estimates should be independent of other projects" is not typically emphasized, as dependencies might exist between projects.