QuestionMay 26, 2025

What must an employer do before you start working in a 10-foot-deep trench? Determine that you are only digging into Type A soil or solid rock. Call a structural engineer to design the trench. Slope, shore, or brace the trench walls. Assign a spotter to monitor signs of trench collapse.

What must an employer do before you start working in a 10-foot-deep trench? Determine that you are only digging into Type A soil or solid rock. Call a structural engineer to design the trench. Slope, shore, or brace the trench walls. Assign a spotter to monitor signs of trench collapse.
What must an employer do before you start working in a
10-foot-deep trench?
Determine that you are only digging
into Type A soil or solid rock.
Call a structural engineer to design the
trench.
Slope, shore, or brace the trench walls.
Assign a spotter to monitor signs of
trench collapse.

Solution
4.2(308 votes)

Answer

Slope, shore, or brace the trench walls. Explanation Before starting work in a trench, employers must ensure safety measures are in place to prevent collapses. This includes sloping, shoring, or bracing the walls of the trench to protect workers from potential hazards.

Explanation

Before starting work in a trench, employers must ensure safety measures are in place to prevent collapses. This includes sloping, shoring, or bracing the walls of the trench to protect workers from potential hazards.