QuestionApril 30, 2025

Employees must not work on scaffold surfaces until: A. The surfaces are determined to have the strength and structural integrity to support their intended loads B. OSHA has visited the site and inspected the scaffold C. All surfaces are completely dry D. All the above

Employees must not work on scaffold surfaces until: A. The surfaces are determined to have the strength and structural integrity to support their intended loads B. OSHA has visited the site and inspected the scaffold C. All surfaces are completely dry D. All the above
Employees must not work on scaffold surfaces until:
A. The surfaces are determined to have the strength and structural integrity to
support their intended loads
B. OSHA has visited the site and inspected the scaffold
C. All surfaces are completely dry
D. All the above

Solution
4.2(125 votes)

Answer

A. The surfaces are determined to have the strength and structural integrity to support their intended loads Explanation Employees should only work on scaffold surfaces that are safe and structurally sound. This includes ensuring the strength of the scaffolding, compliance with OSHA regulations, and safety from wet conditions. However, not all options must be met simultaneously.

Explanation

Employees should only work on scaffold surfaces that are safe and structurally sound. This includes ensuring the strength of the scaffolding, compliance with OSHA regulations, and safety from wet conditions. However, not all options must be met simultaneously.