question
A new system addition to the building is tied into the
existing system mains using a rolling offset.The
rolling offset consists of two flanged 22(1)/(2)^circ ells and a
diagonal pipe assembly. The main pipe size is 6".The
new main location is 1' higher and offset 2
horizontally from the existing main. The center-to
center measurement of the offset pipe assembly is
__
Round decimals to three places.Round all fractions
to the nearest (1)/(8)th Refer to the appendix for fitting
takeouts and allowances.
Select one:
a. 5'-10(1)/(8)''
b. 5'-2(5)/(8)''
C. . 6'
d. 9'-10(1)/(8)''
e. 8'